The construction

Phase Three

The third phase of the construction began at the end of September and was completed in November 2013. With the main building structure and roof completed in the previous phases the third phase began with the construction of the concrete floors in the classrooms, offices and the veranda. Once the floors were set the walls were sealed and plastered to strengthen the building. The local engineers then made and installed the steel windows and doors to provide the security to the building. The community then rallied round to support the painting of the school, which finished the building and resulted in the whole construction taking under 7 months to complete.